NECPs process
National Energy and Climate Plans (NECPs) are a central planning tool for Contracting Parties to define and implement their 2030 energy and climate objectives in line with Energy Community targets.
The NECP process is a joint effort between Contracting Parties and the Energy Community Secretariat. While each country leads its own planning, the Secretariat supports the process by encouraging regional cooperation, promoting consistent methodologies, and providing feedback and recommendations where needed.
This page provides an overview of the current state of NECP implementation across the Energy Community, as well as background on the process and key milestones.
USEFUL LINKS
Albania
Document | Date | |
---|---|---|
![]() |
Draft NECP | submitted May 2021 |
![]() |
Secretariat's Recommendation | published 17 December 2021 |
![]() |
Adopted NECP | published December 2021 |
Bosnia and Herzegovina
Document | Date | |
---|---|---|
![]() |
Draft NECP | submitted 30 June 2023 |
![]() |
Secretariat's Recommendation | published 29 December 2023 |
Georgia
Document | Date | |
---|---|---|
![]() |
Draft NECP | submitted 21 July 2023 |
![]() |
Secretariat's Recommendation | published 29 December 2023 |
![]() |
Adopted NECP | adopted 27 June 2024 |
Kosovo*
Document | Date | |
---|---|---|
![]() |
Draft NECP | submitted 10 July 2023 |
![]() |
Secretariat's Recommendation | published 29 December 2023 |
North Macedonia
Document | Date | |
---|---|---|
![]() |
Draft NECP | submitted June 2020 |
![]() |
Secretariat's Recommendation | published 20 November 2020 |
![]() |
Adopted NECP | published 31 May 2022 |
Serbia
Document | Date | |
---|---|---|
![]() |
Draft NECP | submitted 29 June 2023 |
![]() |
Secretariat's Recommendation | published 13 November 2023 |
![]() |
Adopted NECP | published 25 July 2024 |
Moldova
Document | Date | |
---|---|---|
![]() |
Draft NECP | submitted 13 December 2023 |
![]() |
Secretariat's Recommendation | published 3 April 2024 |
![]() |
Adopted NECP | published 26 February 2025 |
Ukraine
Document | Date | |
---|---|---|
![]() |
Draft NECP | submitted 2 May 2024 |
![]() |
Secretariat's Recommendation | published 5 June 2024 |
![]() |
Adopted NECP | adopted 25 June 2024 |
Montenegro
Document | Date | |
---|---|---|
![]() |
Draft NECP | submitted 9 December 2024 |
![]() |
Secretariat's Recommendation | published 31 March 2025 |
Background
-
Governance Regulation
The Governance Regulation in the Energy Community requires Contracting Parties to develop integrated National Energy and Climate Plans (NECPs). The NECPs include national objectives and targets and respective policies and measures for all five dimensions of the Energy Union, which are closely related and mutually reinforcing, namely:
- decarbonisation (including renewable energy);
- energy efficiency;
- energy security;
- internal energy market; and
- research, innovation and competitiveness.
-
Structure and analysis
The mandatory structure and the content of the NECPs is outlined in Annex I of the Governance Regulation and includes the following:
- Overview and process for establishing the Plan
- National objectives and targets;
- Policies and measures;
- Current situation and projections with existing policies and measures;
- Impact assessment of planned policies and measures.
In their NECPs, Contracting Parties need to compare how their energy system and their greenhouse gas emissions will develop under existing and under new policies and measures. The underlying assessment requires robust modelling capacity and can benefit from regional coordination.
-
Deliverables deadlines in detail
When preparing their NECPs, Contracting Parties should undertake public consultations, establish a multilevel climate and energy dialogues and cooperate with each other and with Member States of the European Union.
The Governance Regulation lays out the schedule for submitting the draft and the adopted NECPs to the Energy Community Secretariat, as well as for submitting NECP Updates and Integrated Progress Reports. Ahead of the respective deadlines, Contracting Parties are invited to share preliminary drafts or draft chapters of the NECPs with the Energy Community Secretariat for informal comments.
Deliverable Period covered
Draft version to be submitted
to EnC Secretariat byFinal version to be notified
to EnC Secretariat by1st NECP 2025-2030 30. June 2023 30. June 2024 NECP Progress Report 15. March 2025 NECP Progress Report 15. March 2027 NECP Progress Report 15. March 2029 2nd NECP 2031-2040 1. January 2028 1. January 2029 NECP Progress Report 15. March 2031 NECP Progress Report 15. March 2033 Update of 2nd NECP 2031-2040 1. January 2033 1. January 2034 NECP Progress Report 15. March 2035 NECP Progress Report 15. March 2037 NECP Progress Report 15. March 2039 3rd NECP 2031-2040 1. January 2033 1. January 2034