Brief project description
New interconnection between the power systems of Serbia, Bosnia and Herzegovina and Montenegro is planned to be realized by the 400 kV transmission lines between the substation 400/220/110 kV Pljevlja 2 in Montenegro, the substation 400/220/35 kV Bajina Bašta in Serbia and the substation 400/110 kV Višegrad in Bosnia and Herzegovina (at the moment there are 220 kV lines at the same or similar routes between these countries). A necessary precondition for this investment is a realisation of section 3 of the Trans Balkan corridor, which is a new 2x400 kV line between substations Obrenovac and Bajina Basta in Serbia, together with upgrading the substation 220 kV Bajina Bašta with the 400 kV voltage level. On Montenegrin side, line 400 kV Cevo – Pljevlja has also to be finished. EMS plans to finish this investment in 2027.
The new 400 kV transmission line between Serbia and Montenegro will be built as a double-system circuit line but equipped with one circuit in the first phase. In Montenegro, the project also includes the reconstruction and expansion of the substation in Pljevlja with the 400 kV busbars. With the construction of the new transmission line 2x400 kV Pljevlja - Bajina Bašta, transmission line 220 kV Bajina Bašta – Pljevlja will be dismantled, and its corridor will be used for the new 2x400kV transmission line.
With the implementation of this project across three countries, more efficient operation of the HVDC link between Montenegro and Italy will be ensured, increasing possible exchanges over the borders of all countries involved in the project.
Expected benefits:
- Increase of the NTC values between Serbia and Montenegro, and Serbia and Bosnia and Herzegovina;
- Increasing the security of supply in all three countries;
- Supporting RES integration.
-
Basic project data
Descriptions Bosnia and Herzegovina Montenegro Project promoter company/Organization full name Independent System Operator in Bosnia and Herzegovina (Nezavisni operator sistema u BiH, NOS BiH)
Joint Stock Company – Montenegrin Transmission System Operator (CGES) Shareholders of the project promoter company
Federation of Bosnia and Herzegovina (Bosnia and Herzegovina)
Republic of Srpska (Bosnia and Herzegovina)
Joint Stock Company – Montenegrin Transmission System Operator (Montenegro)
including: Elektromreza Srbije AD Project impact as described by the project promoters Increasing NTC between RS, BA and ME, enabling and supporting RES integration in the region, better utilisation of HVDC MONITA together with its upgrading, and further electricity market integration. Increased security of the electricity supply.
Is the project cross-border? YES Is the project internal (national) and has a cross-border impact? NO Project ID in ENTSO-E TYNDP 2022: 227 Project ID in ENTSO-E TYNDP 2024: 227 Was the project included in any of the previous PECI processes? YES (PECI 2016, PECI 2018, PECI 2020)
Project in National Network Development Plan (NNDP): YES
YES
Project Name in National NDP / Infrastructure Plan: DV 400 kV Višegrad – Bajina Bašta Constraction 400 kV Pljevlja 2 - Bajina Bašta – Višegrad Full name of the NNDP: Dugoročni plan razvoja prenosne mreže Bosne i Hercegovine 2021 - 2030. - Knjiga I Transmission system Development plan of Montenegro 2023-2032 National NDP/infrastructure plan publication website NOS BiH website CGES website Are there any other internal or cross-border projects depending on the realisation of the project? YES
Transbalkan Corridor 400 kV Čevo – Pljevlja
YES
Transbalkan Corridor section III Obrenovac (RS) - Bajina Bašta (RS)Any other important/relevant information: N/A -
Technical data
Basic technical data Eligible electricity infrastructure type: Interconnector Type of investment: Construction of new infrastructure Expected year of commissioning: 2027 Expected lifetime (years): 60 (Montenegro), 70 (Bosnia and Herzegovina) Substation from: Bajina Bašta (Serbia) Substation to: Pljevlja (Montenegro), Višegrad (Bosnia and Herzegovina) Nominal voltage (kV): 400 Single/double circuit: Double-system circuit Maximum capacity (MW): 1200 Nominal apparent power (MVA): 1330 Length (km): 14,95 (Montenegro); 17,1 (Bosnia and Herzegovina) Expected positive influence on the power system stability: YES - transient stability (Montenegro), NO (Bosnia and Herzegovina)
Any other important/relevant information: NO Expected net transfer capacities increase Time frame From country 1
To country 2
Capacity increase from country 1 to country 2 (MW)
Capacity increase from country 2 to country 1 (MW)
2030
ME - Montenegro
RS - Serbia
600
600
2040
ME - Montenegro
RS - Serbia
600
600
2050
ME - Montenegro
RS - Serbia
600
600
2030
BA - Bosnia and Herzegovina
RS - Serbia
300
500
2040
BA - Bosnia and Herzegovina
RS - Serbia
300
500
2050
BA - Bosnia and Herzegovina
RS - Serbia
300
500
Other data Line resistance R (pu): not available Line reactance X (pu): not available Line susceptance B (pu): not available Number of additional substations: 0 Location of the additional substations: not available Capacity of substations (MVA): not available Voltage (kV): not available Planned outage rate, if applicable (%): not available Forced outage rate, if applicable (%): not available Mean time to repair (h): not available Any other important/relevant information: no additional information -
Cost data
CAPEX (real 2022 million EUR)* Year Bosnia and Herzegovina Montenegro Total 2022
0,150
0,290
0,440
2023
0,607
0,297
0,904
2024
0,000
2,000
2,000
2025
0,000
3,320
3,320
2026
3,928
3,646
7,574
2027
2,629
3,646
6,275
2028
-
-
-
2029
-
-
-
2030
-
-
-
2031
-
-
-
2032
-
-
-
2033
-
-
-
2034
-
-
-
2035
-
-
-
2036
-
-
-
2037
-
-
-
2038
-
-
-
2039
-
-
-
2040
-
-
-
2041
-
-
-
2042
-
-
-
2043
-
-
-
2044
-
-
-
2045
-
-
-
2046
-
-
-
2047
-
-
-
2048
-
-
-
2049
-
-
-
2050
-
-
-
TOTAL
7,315
13,199
20,514
* As declared by the project promoters
OPEX (real 2022 million EUR)* Year Bosnia and Herzegovina Montenegro Total 2022
-
-
-
2023
-
-
-
2024
-
-
-
2025
-
-
-
2026
-
-
-
2027
-
-
-
2028
0,025
0,073
0,098
2029
0,027
0,077
0,104
2030
0,028
0,079
0,107
2031
0,029
0,082
0,111
2032
0,031
0,085
0,116
2033
0,033
0,089
0,122
2034
0,035
0,095
0,130
2035
0,039
0,101
0,140
2036
0,043
0,110
0,154
2037
0,049
0,121
0,171
2038
0,057
0,135
0,192
2039
0,066
0,152
0,218
2040
0,076
0,172
0,249
2041
0,089
0,195
0,283
2042
0,102
0,219
0,321
2043
0,115
0,244
0,359
2044
0,128
0,269
0,397
2045
0,141
0,292
0,433
2046
0,152
0,313
0,465
2047
0,162
0,332
0,493
2048
0,170
0,348
0,518
2049
0,178
0,362
0,539
2050
0,025
0,380
0,380
TOTAL
1,775
4,325
6,100
* As declared by the project promoters
-
Status data
Completed phases YES / NO Bosnia and Herzegovina
Montenegro
Consideration phase
YES
YES
Pre-feasibility study
YES
YES
Technical feasibility study
YES
YES
Economic feasibility study (Cost-benefit analysis)
YES
YES
Environmental impact assessment
YES
NO
Detailed design study
YES
NO
Resolved financing
NO
NO
Obtained approvals/permits
NO
NO
Approval by the regulatory authority(ies)
NO
NO
Final investment decision
NO
NO
Tendering procedure
NO
NO
Construction
NO
NO
Planned implementation schedule Year Bosnia and Herzegovina
Montenegro
Consideration phase
2024
Pre-feasibility study
06/2013
06/2013
Technical feasibility study
09/2013
09/2013
Economic feasibility study (Cost-benefit analysis)
03/2014-10/2022
03/2014-10/2022
Environmental impact assessment
03/2014-09/2022
03/2014-09/2022
Detailed design study
03/2020
03/2020
Resolved financing
01/2023
01/2023
Obtained approvals/permits
2025
1/2023
Approval by the regulatory authority(ies)
2025
6/2025
Final investment decision
2025
1/2025
Tendering procedure
2025
1/2025
Construction
2025/2026
12/2025
Commissioning
2026
2026
Other data Does the project have a significant environmental impact: NO A brief description of the nature of the impact: N/A If the project was included in previous PECI lists, description of the actions taken since inclusion in the list: Detailed design study, Environmental impact assessment, Technical feasibility study, CBA
The major risk/barriers affecting the project implementation: - Failure to adopt planning documents (Montenegro);
- Resolving financing and obtaining approvals/permits (Bosnia and Herzegovina)
Risk/barriers mitigation measures: To start obtaining permits (Montenegro, Bosnia and Herzegovina) Is the investment project already applied for financing? YES (Montenegro, Bosnia and Herzegovina) If financial support has been already granted, the amount of support (in real 2022 million EUR): Montenegro - Investment grant WBIF total: € 25,540,000 The investments grant in Montenegro comprises the construction of a new 400 kV transmission line from Lasta to Pljevlja and then to the border with Serbia, including the construction of a new substation in Lastva, the grid connection from Lastva substation to the existing 400kV Podgorica – Trebinje line, and the upgrade of the 400/220/110 kV substation in Pljevlja. The project includes the cost of dismantling the existing 220 kV overhead lines between the substation in Pljevlja and the Montenegro/Serbia border.
Bosnia and Herzegovina - Technical Assistance provided for the complete regional project (Serbia, Bosnia and Herzegovina, Montenegro), within two assignments: 2013 - 2015 (WB5-REG-ENE-02 subproject): 850,000 EUR (BiH portion approx. 30%, not strictly determined), 2018 - 2022 (WB13-REG-ENE-01 subproject): 1,100,000 EUR (BiH portion approx. 15%, not strictly determined).
If financial support has already been granted, the source of financing: Montenegro - The European Commission, together with KfW Development Bank and the European Bank for Reconstruction and Development, provided financial assistance for project identification and preparation, under the Western Balkans Investment Framework Grant WB-IG00-MNE-ENE-01
Bosnia and Herzegovina - Western Balkans Investment Framework (WBIF) Grant, WB5-REG-ENE-02 subproject implemented by IPF1 and IPF4 Consortium,
and WB13-REG-ENE-01 subproject implemented by IPF7 ConsortiumOther information regarding the current project status: Montenegro - Preparation of tender documents for the selection of contractors.
Bosnia and Herzegovina - The project is being reconsidered due to the rise in CAPEX since the feasibility study was completed in 2022.
-
Contact data
Bosnia and Herzegovina Montenegro Contact name:
Mato Zaric
Nemanja Pandurevic
Ana Kijanović
Organisation:
Elektroprenos - Elektroprijenos BiH
Nezavisni operator sistema u BiH
Montenegrian transmision system operator CGES
Country:
Bosnia and Herzegovina
Bosnia and Herzegovina
Montenegro
Position:
General manager
General manager
Engineer for project preparation
-
Results of the evaluation (CBA analysis)
Calculated project benefits
Specific criteria
Indicator
Unit
2030
2040
2050
Market integration
B1. Socio-economic Welfare
mil EUR/yr
4.20
7.77
11.96
Sustainability
B2, Additional societal benefit due to CO2 variation
Tons/yr
27,108
31,893
0
mil EUR/yr 2.05
11.19
0
Energy efficiency
B5. Variation in Grid Losses
MWh/yr
28,645
31,642
34,953
mil EUR/yr 2.37
3.07
3.58
Security of Supply
B6. Security of Supply: Adequacy
MWh/yr
-
3,550
-28.070
mil EUR/yr -
10.65
-84.21
CBA results
Economic indicator
Unit
Result
NPV
mil EUR
59.95
B/C
-
3.78